| |
Dredging at
Port Klang for bigger ships on
target
NST Logistics 22 January 2007
Deepening of
the Northern Approach Channel
at Port Klang to allow bigger
and deep draft vessels to call
at Northport is making good
progress and is expected to be
completed before end of the
year.
Integrated Marine Works Sdn
Bhd, a subsidiary of
Malaysia’s dredging giant,
Inai Kiara Sdn Bhd, said
almost 60 per cent of the
dredging of the Channel has
been completed.
The company has deployed a
versatile 126m trailing
suction hopper dredger, Mv
Inai Tulip to remove the
spoils from the seabed and
“work is progressing
round-the-clock to remove the
deposits from the Channel”.
To date, the dredger has
removed more than 12 million
cubic metres of deposits from
the Channel to allow better
under keel clearance for
bigger and deep draft vessels
to navigate the channel to
safely berth at Port Klang.
Inai Tulip has a hull in the
shape of a conventional ship,
and is highly seaworthy and
able to operate without any
form of mooring or spud.
The self-propelled ship went
through a major refurbishing
at Singapore Technologies
Marines recently and was
delivered to Inai Kiara in
2005.
“The dredger has since been
deployed on the job at Port
Klang,” said the master of
Inai Tulip, Capt Mohd Anizi.
Inai Tulip which built by IHC
Holland, Kinderdijk is
equipped with twin (one on
each side) trailing suction
pipes with 1,000mm diameter.
Materials that are dredged
from the sea are lifted
through the trailing pipes and
discharged into an 8,000 cubic
metre hopper contained within
the hull of the dredger.
The dredger which has the
capability to dredge up to 25
metre-33 metre depth operates
very much like a floating
vacuum cleaner. The trailing
suction hopper dredger
operates by skimming off
layers of materials from the
seabed.
The suction pipe, linked with
a draghead, is incorporates a
water-jet system and blades
and other means of dislodging
compacted materials. The
draghead allows the materials
to flow to the suction inlet
as efficiently as possible.
The dredged materials are
mixed with water, pumped up,
and then discharged into
hopper.
There the heavy material
settles, and the surplus water
is overflow to the sea.
“When we dredge we normally
sail at a speed of 1.5 knots
when the dredging work is in
progress and its takes between
one and half to two hours for
us to fill up the hopper with
some 7,000 cubic metre
material,” said Capt Anizi.
Once the hopper is full, Inai
Tulip will sail like any other
ordinary ships at 10 knots
towards the West Channel
dumping ground located some
twenty nautical miles away.
The dump is an area identified
by the government.
“It takes about two hours for
us to reach the dumping ground
and when the dredger reaches
above the ground, the doors
below the hull are released
slowly to ensure that the
dumping materials are disposed
evenly on the seabed. The
doors are then closed again
and the dredger is back to
dredging site at 14 knots,”
explained Capt Anizi.
Capt Azizi said an average
cycle takes about 6 hours.
“We work with 30 crew members
and work 24 hours. We complete
four round-trips in a day,”
said Capt Mohd Anizi.
He said the trailing suction
hopper dredger used is one of
the best methods as it allows
economic transfer of the
dredged materials, especially
for dredging of approach
channels or reclamation
projects.
When the dredging work is
completed by end of this year,
the dredger would have removed
22.62 million cubic metre
deposits from the approach
channel and will pave way for
the bigger vessels to reach
Northport via Pulau Angsa
passage through Northport
Channel.
The multi-million dredging
work is being carried out in
six parcels (1A, 1B, 1C, 2A,
2B and 2C). The sector from
Sarang Lang to Buoy 14 will
dredged to 15.5 metres and
from Buoy 14 to Pulau Angsa is
being dredged to 13.5 metre.
BACK
TO NEWS PAGE
|
|